Kano State Urban Planning and Development Authority (KNUPDA)
These guidelines outline the procedure for obtaining Right of Way (ROW) approval for infrastructure development such as fibre optic cables, pipelines, utilities, and related works within Kano State.
All applicants must obtain approval from the Kano State Urban Planning and Development Authority (KNUPDA) before commencing any ROW-related activity.
Applicants are required to submit a formal application letter addressed to:
The Managing Director
Kano State Urban Planning and Development Authority (KNUPDA)
The application should include:
Approved ROW/Engineering Charges
📡 FIBRE OPTIC CABLES
| Description | Unit | Urban Rate (₦) | Rural Rate (₦) | Levy |
| Normal Trenching | Per meter | 1,500 | 1,000 | |
| Surface Dressing (Shoulders) | Per meter | 2,000 | 2,000 | |
| Asphaltic Road Cutting | Per meter | 15,000 | 15,000 | |
| Interlocking Tiles | Per meter | 5,000 | 5,000 | |
| Thrust Boring | Per meter | 15,000 | 15,000 | |
| Concrete Breaking | Per meter | 5,000 | 5,000 |
👉 Levy: ₦3,000,000 OR 50% of project cost (whichever is higher)
Additional Charges
| Description | Unit | Rate |
| Tenement Rate (Annual) | Per meter | ₦20 |
| Planning Permit (Federal Road) | Per meter | Urban: ₦750 / Rural: ₦500 |
| Levy | — | ₦2,000,000 |
Aerial Cabling (Special Cases)
| Description | Unit | Rate | Levy |
| Aerial Cable | Per meter | ₦750 | ₦1,000,000 |
| Pole | Per pole | ₦5,000 | ₦1,000,000 |
🚰 WATER / ELECTRICITY CABLES (INDIVIDUALS)
| Description | Unit | Urban (₦) | Rural (₦) |
| Normal Trenching | Per meter | 1,500 | 1,000 |
| Surface Dressing | Per meter | 2,000 | 2,000 |
| Interlocking Tiles | Per meter | 2,000 | 2,000 |
| Asphalt Cutting | Per meter | 10,000 | 10,000 |
| Thrust Boring | Per meter | 5,000 | 5,000 |
| Concrete Breaking | Per meter | 2,000 | 2,000 |
👉 Levy: ₦50,000
👉 Additional: +50% of total charges
🚧 ROAD ACCESS (OPENING ON ROAD ELEMENTS)
Access Slabs
| Type | Unit | Rate (₦) | Levy |
| Filling Station | Per meter | 40,000 | +100% |
| Industrial | Per meter | 40,000 | +100% |
| Commercial (Banks, Hotels, etc.) | Per meter | 20,000 | +50% |
| Residential | Per opening | 30,000 – 50,000 | +50% |
👉 Note: Depends on location
U-Turn Provision
| Type | Unit | Rate (₦) | Levy |
| Crash Barriers | Per meter | 80,000 | +50% |
| Road Median | Per meter | 50,000 | +50% |
| Median Kerbs | Per meter | 50,000 | +50% |
Right of Way (Borehole Drilling)
| Type | Unit | Rate (₦) | Levy |
| Commercial | Per borehole | 50,000 | +50% |
| Residential | Per borehole | 30,000 | +50% |
KEDCO Installations
| Type | Unit | Rate (₦) | Levy |
| High Tension Poles | Per pole | 10,000 | +50% |
| Low Tension Poles | Per pole | 5,000 | +50% |
| Transformer | Per unit | 200,000 | +50% |
Access Road Structures
| Description | Unit | Rate (₦) | Levy | Remark |
| Metal Security Gate | Per gate | 250,000 | +50% | ₦25,000 annual renewal |
Others
| Description | Unit | Rate (₦) | Levy | Remark |
| Internet Service Providers (Mast) | Per unit | 50,000 | +50% | |
| Road Ramp (Speed Breaker) | Per unit | 2,000 | +100% | Excludes public/religious places |
| Item | Unit | Rate |
|---|---|---|
| ISP Mast / Tower | Per structure | 5,250,000 |
| Antenna Installation | Per unit | 5,250,000 |
| Base Station (BTS) | Per site | 5,250,000 |
The Right of Way approval process ensures:
Applicants are advised to comply fully with these guidelines.