📄 GUIDELINES FOR RIGHT OF WAY (ROW) APPROVAL

Kano State Urban Planning and Development Authority (KNUPDA)


🧾 1. INTRODUCTION

These guidelines outline the procedure for obtaining Right of Way (ROW) approval for infrastructure development such as fibre optic cables, pipelines, utilities, and related works within Kano State.

All applicants must obtain approval from the Kano State Urban Planning and Development Authority (KNUPDA) before commencing any ROW-related activity.


📂 2. APPLICATION REQUIREMENT

Applicants are required to submit a formal application letter addressed to:

The Managing Director
Kano State Urban Planning and Development Authority (KNUPDA)

The application should include:

  • Description of proposed project
  • Location and route details
  • Scope of work
  • Project drawings/layout (where applicable)
  • Contact details of applicant

🧾 3. APPLICATION PROCESS

Step 1: Submission

  • Submit formal application to KNUPDA

Step 2: Technical Assessment

  • The application is forwarded to the Engineering Department
  • Technical evaluation of:
    • Route alignment
    • Impact on infrastructure
    • Compliance with planning standards

Step 3: Demand Notice

  • Upon successful assessment, a Demand Notice is issued to the applicant
  • This outlines:
    • Applicable fees

      Approved ROW/Engineering Charges

      📡 FIBRE OPTIC CABLES

      Description Unit Urban Rate (₦) Rural Rate (₦) Levy
      Normal Trenching Per meter 1,500 1,000
      Surface Dressing (Shoulders) Per meter 2,000 2,000
      Asphaltic Road Cutting Per meter 15,000 15,000
      Interlocking Tiles Per meter 5,000 5,000
      Thrust Boring Per meter 15,000 15,000
      Concrete Breaking Per meter 5,000 5,000

      👉 Levy: ₦3,000,000 OR 50% of project cost (whichever is higher)

       

      Additional Charges

      Description Unit Rate
      Tenement Rate (Annual) Per meter ₦20
      Planning Permit (Federal Road) Per meter Urban: ₦750 / Rural: ₦500
      Levy ₦2,000,000

       

      Aerial Cabling (Special Cases)

      Description Unit Rate Levy
      Aerial Cable Per meter ₦750 ₦1,000,000
      Pole Per pole ₦5,000 ₦1,000,000

       

      🚰 WATER / ELECTRICITY CABLES (INDIVIDUALS)

      Description Unit Urban (₦) Rural (₦)
      Normal Trenching Per meter 1,500 1,000
      Surface Dressing Per meter 2,000 2,000
      Interlocking Tiles Per meter 2,000 2,000
      Asphalt Cutting Per meter 10,000 10,000
      Thrust Boring Per meter 5,000 5,000
      Concrete Breaking Per meter 2,000 2,000

       

      👉 Levy: ₦50,000
      👉 Additional: +50% of total charges

      🚧 ROAD ACCESS (OPENING ON ROAD ELEMENTS)

      Access Slabs

      Type Unit Rate (₦) Levy
      Filling Station Per meter 40,000 +100%
      Industrial Per meter 40,000 +100%
      Commercial (Banks, Hotels, etc.) Per meter 20,000 +50%
      Residential Per opening 30,000 – 50,000 +50%

       

      👉 Note: Depends on location

      U-Turn Provision

      Type Unit Rate (₦) Levy
      Crash Barriers Per meter 80,000 +50%
      Road Median Per meter 50,000 +50%
      Median Kerbs Per meter 50,000 +50%

       

      Right of Way (Borehole Drilling)

      Type Unit Rate (₦) Levy
      Commercial Per borehole 50,000 +50%
      Residential Per borehole 30,000 +50%

       

      KEDCO Installations

      Type Unit Rate (₦) Levy
      High Tension Poles Per pole 10,000 +50%
      Low Tension Poles Per pole 5,000 +50%
      Transformer Per unit 200,000 +50%

       

      Access Road Structures

      Description Unit Rate (₦) Levy Remark
      Metal Security Gate Per gate 250,000 +50% ₦25,000 annual renewal

       

      Others

      Description Unit Rate (₦) Levy Remark
      Internet Service Providers (Mast) Per unit 50,000 +50%
      Road Ramp (Speed Breaker) Per unit 2,000 +100% Excludes public/religious places

      📡 ISP / TELECOM INFRASTRUCTURE

      Item Unit Rate
      ISP Mast / Tower Per structure 5,250,000
      Antenna Installation Per unit 5,250,000
      Base Station (BTS) Per site 5,250,000

    • Conditions for approval

Step 4: Payment

  • Applicant makes payment as indicated in the Demand Notice
  • Payment must be made via approved government channels

Step 5: Approval Issuance

  • Upon confirmation of payment, KNUPDA issues:
    • Right of Way Approval Notice
    • Conditions of execution

⏳ 4. PROCESSING TIME

  • The entire process shall be completed within five (5) working days, provided:
    • All required documents are submitted
    • Payment is made promptly

📜 5. CONDITIONS OF APPROVAL

  • Work must strictly follow approved route and specifications
  • Any damage to public infrastructure must be repaired by the applicant
  • Proper safety measures must be observed
  • Relevant agencies must be notified before commencement

⚠️ 6. IMPORTANT NOTES

  • No excavation or installation shall commence without approval
  • Unauthorized works may result in penalties or stoppage
  • Applicants must comply with all regulatory requirements

✅ 7. CONCLUSION

The Right of Way approval process ensures:

  • Protection of public infrastructure
  • Proper coordination of development activities
  • Efficient service delivery

Applicants are advised to comply fully with these guidelines.